Reconstruction Summary
- Driveway and Roadway Culvert additions / improvements
- Ditch Widening and Sloping, drainage improvements
- Road Rehabilitation
- Cross-Fall Corrections
Quantities Summary
Road / Shoulder Excavation + Granular
Total material excavated and removed offsite (shoulder cuts, earth ex): 26000 m3
Total Aggregate Tonnage: 27000 T
Culverts
375mm – 450mm Diameter Culverts HDPE 350 lm