Project: Rowanwood Avenue Road and Watermain Construction
Client: Brantford
Start Date: 04/10/2017
End Date: 06/01/2017
Budget: $424,748.00

Reconstruction Summary

  • Upgrade from duct iron Watermain
  • Replacement of curb and cutter, sidewalks
  • Replacement of Roadway
  • Copper water service to property line
  • Replacing deficient sanitary laterals

 

Quantities Summary

Catchbasins: 3

Double Catchbasins: 4

Watermain: 150mm diameter 232 lm

Hydrants: 2